Log Home Construction Progress - Page 3
March 6, 1999
The logs in the gables were put in place, some more rafter work was done and the porch floor was built.
 Back - 3/6/99 |
 Front - 3/6/99 |
March 13, 1999
The porch was completed, front dormers framed and they began decking the roof with tounge-and-groove 1x6's (the first of many layers of roofing - T&G, 15# felt, 2 layers of 1.5" thick foam insulation, 1x6 vertical strips, OSB decking, 30# felt, then shingles).
 Front - 3/13/99 |
 Back - 3/13/99 |
March 20, 1999
Most of the roof has all layers up to the felt and the dormers have the log siding on their sides.
 Front - 3/20/99 |
 Back - 3/20/99 |
March 28, 1999
The log crew finished up late Saturday evening (3/27) by putting in the doors and windows as the finishing touch.
 Front - 3/28/99 |
 Back - 3/28/99 |

Right side - 3/28/99